Showing posts with label project manager. Show all posts
Showing posts with label project manager. Show all posts

Thursday, 6 February 2014

BORED PILING METHOD STATEMENT

BORED PILING METHOD STATEMENT.


WORK PROCEDURE

















WORK PROCEDURE




PROJECT:



Ref No. FOUN/04



PAGE 1 OF 2



SECTION:


FOUNDATIONS



DATE OF ISSUE


Dec 2012



SUBJECT:


BORED PILING



BY:


QA/QC ENGINEER



APPROVED BY:


QEHS MANAGER



ACTION



VERIFY



1.    SCOPE


The scope of this procedure covers the control of installation of Bored Cast-in-Situ Concrete piles executed by a sub-contractor.


2.    PROCEDURE


.1    Method Statement:


A method statement shall be submitted by the piling Sub-contractor for approval which shall include:


i)    Construction procedure.


ii)    Pile design with calculations.


iii)    Testing procedure.


iv)    Documentation to be maintained during the execution of work.


v)    Mix design for concrete.


vi)    Specification for reinforcement steel and bentonite clay.


vii)    Any other information required by the specification.


.2    Construction Programme:


The sub-contractor shall submit a programme for approval based on the Contract Programme. The subcontractor shall also indicate the mobilisation time of plant, equipment, materials and work force.


.3    Piling Sequence:


Approval of piling sequence will be given prior to commencement of piling by the Subcontractor.


.4    Setting-Out:


HEE will execute pre-piling setting out and offer for cross-checking by Subcontractor’s Surveyor and Consultant’s Representative.



Project


Manager


Sub-contractor


Project


Manager


Subcon/


FCC Surveyor


Method


Statement


Approved


Construction Programme


Approval


Field Book





















PROJECT:



Ref No. FOUN/04



PAGE 2 OF 2



SECTION:


FOUNDATIONS



DATE OF ISSUE


Dec 2012



SUBJECT:



BY:


QA/QC ENGINEER



BORED PILING



APPROVED BY:


QHSE MANAGER



ACTION



VERIFY



.5    Source Certificates:


Reinforcement steel and Bentonite test certificates if required shall be obtained from the Subcontractor and, submitted for approval by the Consultant.


.6    Concrete Cube Testing:


Cube results will be assessed and retained. The cube test reports shall be clearly identified with the location of pour by reference to the checksheet.


.7    Testing of Piles:


The Subcontractor shall carry out a load test and integrity test as specified in the Contract.


.8    Inspection of Work/Checksheet:


The work shall be inspected using the attached checksheet as Appendix FOUN/04/A which shall be completed as verification and record of compliance.


.9    Non-Conformity:


Non-conforming workmanship shall be notified to the Subcontractor as Appendix 7/3/6/A and corrective action taken in accordance with good working practice and Consultants approval.



Project Engineer


Project Engineer/


Labtech.


Subcon.


QA/QC


QA/QC



Source certificate


Test result, FOUN/04/A


Pile testing record


Checksheet


Non-


Conformity Report























































































CM – Construction Manager, QA/QC – Quality Assurance/Quality Control, PE – Project Engineer, SE – Site Engineer, GF – General Foreman, SU – Surveyor, Lab – Laboratory Technician


DOWNLOAD BORED PILING METHOD STATEMENT WORD TEMPLATE: BORED PILING



BORED PILING METHOD STATEMENT
PROJECT:                        SITE NO.:

CHECK SHEET FOR BORED PILING


Sheet No.


SUBCONTRACTOR: FATAYERJI


SECTION OF WORK ____________________________LOCATION _________________


STAGE



ITEM



Checked


by



DATE


PREPARATION1. Subcontractor’s method statement approved.PE
2. Materials approved by the consultant.PE
3. Cross-check location of Pile.SU

APPROVAL TO PROCEEDQA/QC
INSTALLATION4. Check borehole to be filled with Bentonite

slurry at all times.

GF
5. Check cleaning of bottom of borehole.GF
6. Check reinforcement cage.SE
7. Check minimum cover while lowering cage into the borehole.GF
8. Check slump of concrete.Lab
9. Check cut-off level + location.SU
APPROVAL TO PROCEED WITH PILE CAP.CM

Wednesday, 5 February 2014

Excavation, Earthwork and Filling Method Statement

Excavation, Earthwork and Filling Method Statement


WORK PROCEDURE






















Download the Excavation, Earthwork and Filling Method Statement word document: EXCAVATION, EARTHWORK AND FILLING



Excavation, Earthwork and Filling Method Statement
SUBJECT:

BY:


QA/QC ENGINEER


EXCAVATION, EARTHWORK AND FILLING

APPROVED BY:


QEHS MANAGER



ACTION



VERIFY



1. SCOPE


This procedure provides a standardised framework for the control of excavation, earthwork and filling to ensure compliance with conditions of contract and contract specifications.


2. PROCEDURE


.1 All excavation, earthwork and filling will be carried out in accordance with the specification detailed in the project contract documentation. In any circumstances where specifications are not provided or they are in any way incomplete, the matter shall be referred back to consultant for additional information.


.2 Method Statement


A method statement will be prepared and approved where deemed necessary, and may include:


i) Site plan showing the location of spoil heaps for temporary storage and if appropriate permanent storage area.


ii) Type of plant and equipment to be used.


iii) Means for keeping excavations free of water.


iv) Method of trench supports.


v) Method and sequence of excavation to ensure that no damage is caused to adjoining structures and property. If there is potential for damage to adjoining structures and property, the type of preventative measures should be indicated.


vi) Temporary support arrangement of adjacent structures and services passing through the site.


vii) Method of compacting fill and testing procedure.



  1. Health and Safety requirements.



  2. Any other special requirements.





Project Manager


Project Manager





Method Statement



.3 Existing Utilities



  1. Liaise with all public utility companies e.g. water, electricity, telephone sewerage and surface water etc. to ensure that all the available information on the location of utilities and underground services through and adjacent to the site of the excavation is obtained.


ii) Ensure that utilities and underground services are located on site using markings, which are clearly visible. Ensure those plant operators and operatives involved with the activity are fully aware of the location of the various utilities and underground services and their respective depths.


iii) Where deemed necessary, excavate trial holes to establish the precise location and depth of services.


iv) Plant operators must be aware of overhead cables. Use height control indicators where necessary.


.4 Site Survey and Grid of Levels


Prior to commencement of any excavation work, a level survey will be carried out to confirm the information included on the contract drawings and to provide an accurate record of existing ground levels for the calculation of quantities.


.5 Disposal of Surplus Excavated Material


Prior to any surplus excavated material being removed from the site, documentary evidence of “approval to tip” must be obtained beforehand from the relevant government/municipal departments and the owner of the land where the material is to be tipped.


.6 Adjoining Structures and Property


Prior to the commencement of excavation work, a detailed dilapidation survey will be undertaken to record the existing condition of the adjoining structures and property. Where necessary the survey may include photographic records.



Project Manager


Project Engineer


Project Engineer


Site Engr./


Surveyor


Project Manager





Drawing/


N.O.C.


Markings


Trial Holes


Survey


Approval to Tip





This survey should be carried out in co-ordination with and involving the participation of the Consultant’s representative and the representative of the owners/occupiers of the adjacent property.


.7 Excavation Work



  1. Excavation shall be allowed to progress to the designed formation level less 50mm (unless specified otherwise). The remaining 50mm shall be carried out by further careful excavation to avoid disturbing the formation level.



  1. After reaching the designed formation level, Consultant’s representative shall be requested in writing to inspect and approve the formation prior to the commencement of any subsequent activities.


iii) Great care shall be taken to minimise noise, vibration and dust pollution, which can cause nuisance and damage, particularly if the site is located in a built-up area.


iv) Sides of all excavations should be properly supported using an appropriate method as detailed in the Method Statement.


.8 Filling



  1. Prior to commencement of filling, the Consultant’s representative shall be requested in writing to inspect and approve the fill starting level.


ii) Filling shall be carried out using approved materials in accordance with the specification which can either be selected from the material on site or imported from selected and approved sources.


iii) Filling shall be carried out as per approved method and as per the contract specification.



Const. Manager


Project Engineer


QA/QC


Project Engineer/


Site Safety


Project Engineer/Site Safety


QA/QC


Project Engineer


Project Engineer



Dilapidation


Survey


Survey


Inspection Request


Method Statement


Method Statement


Inspection Request


Source Documents


Method Statement


Sunday, 2 February 2014

PROJECT CLOSE-OUT Template

PROJECT CLOSE-OUT Template in word format with description what is required in each field to fill



 









 


Project Description:




 


 




Project Title:



Date Prepared:


Project Manager:
Provide a summary-level description of the project. This information can be copied from the Project Charter.





 




Project Objectives



Success Criteria



How Met



Variance











 



Scope:
A statement that describes the scope needed to achieve the planned benefits of the projectThe specific and measurable criteria that will determine project successProvide evidence that the success criteria were met.Explain any scope variances.









 



Time:
A statement that describes the goals for the timely completion of the project.The specific dates that must be met to determine schedule success.Identify the date of final delivery. Use the information from the Product Acceptance form.Explain any schedule or duration variances.









 



Cost:
A statement that describes the goals for the project expenditures.The specific currency or range of currency that defines budgetary success.Enter final project costs.Explain any cost variances.









 



Quality:
A statement that describes the quality criteria for the project.The specific measurements that must be met for the project and product to be considered a success.Enter the verification and validation information from the Product Acceptance form.Explain any quality variances.









 


 


Contract Information:



Other:
Any other types of objectives appropriate to the projects.Relevant specific measurable results that define success.Enter the evidence that other objectives have been met.Explain any other variances.

Provide information on contracts. Enter information from the Contract Close-out report.

 


 


 


 




 


 


Approvals:






















 


Download PROJECT CLOSE-OUT Template PROJECT CLOSE-OUT Template



PROJECT CLOSE-OUT Template
Project Manager SignatureSponsor or Originator Signature
Project Manager NameSponsor or Originator Name
DateDate

Thursday, 23 January 2014

PMP Exam Tips

General PMP Exam Tips


General tips – obtained from “PMP Exam Resource”


You should memorize all formulas, especially the Earned Value and PERT.


Practice eliminating the completely implausible options first.


There is no penalty for guessing; thus, do not leave any question blank.


There will always be those situations where you have no idea what the question is asking.


Use educated guessing to select the most appropriate option. Remember, you have only 80 seconds for each question. If you do not know the answer of a question, mark it and move on and revisit it later if you have time.


Answer the questions based on the PMBOK concepts first, then consider your experience.


If they are in conflict, the PMBOK wins.





PMI Concept Oriented Tips


PMI concept-oriented tips – (obtained from “PMP Exam Resource”)


The project manager takes an active approach to the job by not waiting until a risk materializes and becomes a problem. This is an extremely important concept that might affect many questions on an exam. The project manager does not escalate problems to upper management or to the customer before fully analyzing them and identifying options.


When answering a question related to what the project manager should do in a specific situation, you should rephrase the question to: What is the first thing the project manager will do given such a situation and given his or her proactive nature?


Assume that lessons learned and historical databases are available. This might not be true in a real life situation.


PMI does not approve adding extra functionality without benefits or gold plating.


Project managers have all kinds of soft and hard skills.


The Work Breakdown Structures (WBSs) are wonderful tools.


Roles and responsibilities need to be properly defined.





Tips for taking the PMP exam (Part 2)


(obtained from “PMP Resources”)


Passing the PMP exam requires extensive preparation. Use the following tips and techniques as part of that preparation, which should also include developing a comprehensive understanding of the PMBOK concepts and terminology, practicing previous exam questions when possible, and attending a few project management-training courses.

Question-oriented tips


There are certain questions that contain extra information. This information is irrelevant and it does not relate to the correct answer. Beware of such questions and remember it isn’t necessary to use all the information provided to answer the question.


Each question has only one correct answer. You need to select the most appropriate answer. Beware of choices that represent true statements but are not relevant. Be sure to read all the options before you select any one.


You need to answer the questions from a PMI perspective—not from your own perspective, which you acquired through experience. Remember that PMI is trying to present an ideal environment for project managers that might be different from your own experience.


Beware of answer choices that represent generalizations, which may be characterized by words such as always, never, must, or completely; these are often the incorrect choices.


Look out for choices that represent special cases. These choices tend to be correct and are characterized by words such as often, sometimes, may, generally, and perhaps.


The correct answer may not be grammatically correct.





Tips on taking the PMP exam (Part 1)


Tips on taking the PMP exam (taken from “PMP Exam Resource”)


The PMP certification examination is a computer-based exam that is offered at PMI locations in the United States, Canada, and in other countries worldwide.


The exam is based on information from the entire project management body of knowledge. The Guide to the Project Management Body of Knowledge” (PMBOK), which is published by PMI, provides an outline of the topics covered.


Because the exam is computer based, participants can find out how they scored by reading the detailed report on performance that is available when the exam is completed. Questions on the PMP exam are grouped by project management processes. The basic PMP exam is not industry specific. The PMI Certificate of Added Qualification (CAQ), which tests your knowledge of a particular industry, can be added to certify your expertise in Information Technology Project Management, Establishing a Project Management Office, and Project Management in the Automotive Industry.





Tips & Tricks in getting your PMP


treat this as a project: today is your start day and decide a target finish date


become a member of PMI – its is cheaper this way (read FAQ)


register on line and get your approval to write PMP exam within 3 days (read FAQ)


call your exam center and get an exam day


get hold of a PMP mock test and record down your score on each knowledge area


record your weak “knowledge area”


check the literatures to read for PMP (check FAQ) and its review .


important to know your own effective study style (do not just follow somebody’s advice to memorize ITTO)


go through the exam exercises as much as you can, use the PMP/CPAPM Daily Tips


study all the PMIism and for the exam’s sake try to believe in them


visit the exam center several days before the exam, get familiar with the area


get a good rest 2-3 days before the exam


during the exam: stay calm and after 10 minutes or so you will get your rhythm


always choose the best answer for all the possible right answer, eliminate those that are wrong


You should memorize all formulas, especially the Earned Value and PERT.


Practice eliminating the completely implausible options first.


There is no penalty for guessing; thus, do not leave any question blank.


There will always be those situations where you have no idea what the question is asking.


Use educated guessing to select the most appropriate option. Remember, you have only 80 seconds for each question.


If you do not know the answer of a question, mark it and move on and revisit it later if you have time.


Answer the questions based on the PMBOK concepts first, then consider your experience. If they are in conflict, the PMBOK wins



PMP Exam Tips

Project Charter Template

Have you ever wondered how the project charter looks like? in this post i will show you how the project charter could be.



























Project Title:

Project Sponsor:



Date Prepared:



Project Manager:



Project Customer:




Project Purpose or Justification:




Project Description:




Project and Product Requirements:




Acceptance Criteria:




Initial Risks:








Project Objectives



Success Criteria



Person Approving










Scope:








Time:








Cost:








Quality:








Other:






















Summary MilestonesDue Date


Estimated Budget:



Project Manager Authority Level




Staffing Decisions:




Budget Management and Variance:




Technical Decisions:




Conflict Resolution:




Escalation Path for Authority Limitations:

Approvals:

















Date                             Date


 


Download the project charter word form1.01_PCoE_Project_Charter



Project Charter Template
Project Manager SignatureSponsor or Originator Signature
Project Manager NameSponsor or Originator Name
Older Posts Home

Planning EngineerPlanning Engineer

Loading...

مهندس تخطيطمهندس تخطيط

Loading...

Planification IngénieurPlanification Ingénieur

Loading...