Thursday, 6 February 2014

BORED PILING METHOD STATEMENT

BORED PILING METHOD STATEMENT.


WORK PROCEDURE

















WORK PROCEDURE




PROJECT:



Ref No. FOUN/04



PAGE 1 OF 2



SECTION:


FOUNDATIONS



DATE OF ISSUE


Dec 2012



SUBJECT:


BORED PILING



BY:


QA/QC ENGINEER



APPROVED BY:


QEHS MANAGER



ACTION



VERIFY



1.    SCOPE


The scope of this procedure covers the control of installation of Bored Cast-in-Situ Concrete piles executed by a sub-contractor.


2.    PROCEDURE


.1    Method Statement:


A method statement shall be submitted by the piling Sub-contractor for approval which shall include:


i)    Construction procedure.


ii)    Pile design with calculations.


iii)    Testing procedure.


iv)    Documentation to be maintained during the execution of work.


v)    Mix design for concrete.


vi)    Specification for reinforcement steel and bentonite clay.


vii)    Any other information required by the specification.


.2    Construction Programme:


The sub-contractor shall submit a programme for approval based on the Contract Programme. The subcontractor shall also indicate the mobilisation time of plant, equipment, materials and work force.


.3    Piling Sequence:


Approval of piling sequence will be given prior to commencement of piling by the Subcontractor.


.4    Setting-Out:


HEE will execute pre-piling setting out and offer for cross-checking by Subcontractor’s Surveyor and Consultant’s Representative.



Project


Manager


Sub-contractor


Project


Manager


Subcon/


FCC Surveyor


Method


Statement


Approved


Construction Programme


Approval


Field Book





















PROJECT:



Ref No. FOUN/04



PAGE 2 OF 2



SECTION:


FOUNDATIONS



DATE OF ISSUE


Dec 2012



SUBJECT:



BY:


QA/QC ENGINEER



BORED PILING



APPROVED BY:


QHSE MANAGER



ACTION



VERIFY



.5    Source Certificates:


Reinforcement steel and Bentonite test certificates if required shall be obtained from the Subcontractor and, submitted for approval by the Consultant.


.6    Concrete Cube Testing:


Cube results will be assessed and retained. The cube test reports shall be clearly identified with the location of pour by reference to the checksheet.


.7    Testing of Piles:


The Subcontractor shall carry out a load test and integrity test as specified in the Contract.


.8    Inspection of Work/Checksheet:


The work shall be inspected using the attached checksheet as Appendix FOUN/04/A which shall be completed as verification and record of compliance.


.9    Non-Conformity:


Non-conforming workmanship shall be notified to the Subcontractor as Appendix 7/3/6/A and corrective action taken in accordance with good working practice and Consultants approval.



Project Engineer


Project Engineer/


Labtech.


Subcon.


QA/QC


QA/QC



Source certificate


Test result, FOUN/04/A


Pile testing record


Checksheet


Non-


Conformity Report























































































CM – Construction Manager, QA/QC – Quality Assurance/Quality Control, PE – Project Engineer, SE – Site Engineer, GF – General Foreman, SU – Surveyor, Lab – Laboratory Technician


DOWNLOAD BORED PILING METHOD STATEMENT WORD TEMPLATE: BORED PILING



BORED PILING METHOD STATEMENT
PROJECT:                        SITE NO.:

CHECK SHEET FOR BORED PILING


Sheet No.


SUBCONTRACTOR: FATAYERJI


SECTION OF WORK ____________________________LOCATION _________________


STAGE



ITEM



Checked


by



DATE


PREPARATION1. Subcontractor’s method statement approved.PE
2. Materials approved by the consultant.PE
3. Cross-check location of Pile.SU

APPROVAL TO PROCEEDQA/QC
INSTALLATION4. Check borehole to be filled with Bentonite

slurry at all times.

GF
5. Check cleaning of bottom of borehole.GF
6. Check reinforcement cage.SE
7. Check minimum cover while lowering cage into the borehole.GF
8. Check slump of concrete.Lab
9. Check cut-off level + location.SU
APPROVAL TO PROCEED WITH PILE CAP.CM

Wednesday, 5 February 2014

Excavation, Earthwork and Filling Method Statement

Excavation, Earthwork and Filling Method Statement


WORK PROCEDURE






















Download the Excavation, Earthwork and Filling Method Statement word document: EXCAVATION, EARTHWORK AND FILLING



Excavation, Earthwork and Filling Method Statement
SUBJECT:

BY:


QA/QC ENGINEER


EXCAVATION, EARTHWORK AND FILLING

APPROVED BY:


QEHS MANAGER



ACTION



VERIFY



1. SCOPE


This procedure provides a standardised framework for the control of excavation, earthwork and filling to ensure compliance with conditions of contract and contract specifications.


2. PROCEDURE


.1 All excavation, earthwork and filling will be carried out in accordance with the specification detailed in the project contract documentation. In any circumstances where specifications are not provided or they are in any way incomplete, the matter shall be referred back to consultant for additional information.


.2 Method Statement


A method statement will be prepared and approved where deemed necessary, and may include:


i) Site plan showing the location of spoil heaps for temporary storage and if appropriate permanent storage area.


ii) Type of plant and equipment to be used.


iii) Means for keeping excavations free of water.


iv) Method of trench supports.


v) Method and sequence of excavation to ensure that no damage is caused to adjoining structures and property. If there is potential for damage to adjoining structures and property, the type of preventative measures should be indicated.


vi) Temporary support arrangement of adjacent structures and services passing through the site.


vii) Method of compacting fill and testing procedure.



  1. Health and Safety requirements.



  2. Any other special requirements.





Project Manager


Project Manager





Method Statement



.3 Existing Utilities



  1. Liaise with all public utility companies e.g. water, electricity, telephone sewerage and surface water etc. to ensure that all the available information on the location of utilities and underground services through and adjacent to the site of the excavation is obtained.


ii) Ensure that utilities and underground services are located on site using markings, which are clearly visible. Ensure those plant operators and operatives involved with the activity are fully aware of the location of the various utilities and underground services and their respective depths.


iii) Where deemed necessary, excavate trial holes to establish the precise location and depth of services.


iv) Plant operators must be aware of overhead cables. Use height control indicators where necessary.


.4 Site Survey and Grid of Levels


Prior to commencement of any excavation work, a level survey will be carried out to confirm the information included on the contract drawings and to provide an accurate record of existing ground levels for the calculation of quantities.


.5 Disposal of Surplus Excavated Material


Prior to any surplus excavated material being removed from the site, documentary evidence of “approval to tip” must be obtained beforehand from the relevant government/municipal departments and the owner of the land where the material is to be tipped.


.6 Adjoining Structures and Property


Prior to the commencement of excavation work, a detailed dilapidation survey will be undertaken to record the existing condition of the adjoining structures and property. Where necessary the survey may include photographic records.



Project Manager


Project Engineer


Project Engineer


Site Engr./


Surveyor


Project Manager





Drawing/


N.O.C.


Markings


Trial Holes


Survey


Approval to Tip





This survey should be carried out in co-ordination with and involving the participation of the Consultant’s representative and the representative of the owners/occupiers of the adjacent property.


.7 Excavation Work



  1. Excavation shall be allowed to progress to the designed formation level less 50mm (unless specified otherwise). The remaining 50mm shall be carried out by further careful excavation to avoid disturbing the formation level.



  1. After reaching the designed formation level, Consultant’s representative shall be requested in writing to inspect and approve the formation prior to the commencement of any subsequent activities.


iii) Great care shall be taken to minimise noise, vibration and dust pollution, which can cause nuisance and damage, particularly if the site is located in a built-up area.


iv) Sides of all excavations should be properly supported using an appropriate method as detailed in the Method Statement.


.8 Filling



  1. Prior to commencement of filling, the Consultant’s representative shall be requested in writing to inspect and approve the fill starting level.


ii) Filling shall be carried out using approved materials in accordance with the specification which can either be selected from the material on site or imported from selected and approved sources.


iii) Filling shall be carried out as per approved method and as per the contract specification.



Const. Manager


Project Engineer


QA/QC


Project Engineer/


Site Safety


Project Engineer/Site Safety


QA/QC


Project Engineer


Project Engineer



Dilapidation


Survey


Survey


Inspection Request


Method Statement


Method Statement


Inspection Request


Source Documents


Method Statement


Tuesday, 4 February 2014

HUMAN RESOURCE PLAN

HUMAN RESOURCE PLAN


Human Resource Management Plan Template with description of Each Field data, what is required and how to be filled.









 


 




Project Title:



Date Prepared:







 



Roles, Responsibilities, and Authority:
Role:Authority:Responsibility:

  1. Defines the role or job title.









  1. Defines decision-making limits.









  1. Defines the duties.










Project Organizational Structure:
Insert an organizational chart for the project.
May include an organizational chart of the enterprise and how the project fits within the enterprise.
 

 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 




 


 





Staffing Management Plan
Staff Acquisition:
Describes how staff will be brought on to the project. Defines any differences between internal staff team members and outsourced team members with regards to on boarding procedures.

 





Staff Release:
Describes how team members will be released from the team, including knowledge transfer, and check out procedures for staff and outsourced team members.


 





Resource Calendars:
Shows any unusual resource calendars such as abbreviated work weeks, vacations, and time constraints for team members that are less than full time.


 





Training Needs:
Describes any required training on equipment, technology or company processes.
 



 





Rewards and Recognition:
Describes any reward and recognition processes or limitations.
 



 





Regulations, Standards, and Policy Compliance:
Describes any regulations, standards or policies that must be used and how compliance will be demonstrated
 



 





Safety:
Describes any safety regulations, equipment, training, or procedures.
 



 


Download the Microsoft word template for the human resource plan: HUMAN RESOURCE PLAN



HUMAN RESOURCE PLAN

Monday, 3 February 2014

Team work

Team work is the key of success. In the construction projects where the work involved too many parties, There is no way but to work in teams.


Team Work


This photo above show how team members could depend on each other to achieve their goal. In my opinion, individuals who can work effectively in team environment shows much more success and outputs rather than those who prefer to work alone.



Team work

Sunday, 2 February 2014

PROJECT CLOSE-OUT Template

PROJECT CLOSE-OUT Template in word format with description what is required in each field to fill



 









 


Project Description:




 


 




Project Title:



Date Prepared:


Project Manager:
Provide a summary-level description of the project. This information can be copied from the Project Charter.





 




Project Objectives



Success Criteria



How Met



Variance











 



Scope:
A statement that describes the scope needed to achieve the planned benefits of the projectThe specific and measurable criteria that will determine project successProvide evidence that the success criteria were met.Explain any scope variances.









 



Time:
A statement that describes the goals for the timely completion of the project.The specific dates that must be met to determine schedule success.Identify the date of final delivery. Use the information from the Product Acceptance form.Explain any schedule or duration variances.









 



Cost:
A statement that describes the goals for the project expenditures.The specific currency or range of currency that defines budgetary success.Enter final project costs.Explain any cost variances.









 



Quality:
A statement that describes the quality criteria for the project.The specific measurements that must be met for the project and product to be considered a success.Enter the verification and validation information from the Product Acceptance form.Explain any quality variances.









 


 


Contract Information:



Other:
Any other types of objectives appropriate to the projects.Relevant specific measurable results that define success.Enter the evidence that other objectives have been met.Explain any other variances.

Provide information on contracts. Enter information from the Contract Close-out report.

 


 


 


 




 


 


Approvals:






















 


Download PROJECT CLOSE-OUT Template PROJECT CLOSE-OUT Template



PROJECT CLOSE-OUT Template
Project Manager SignatureSponsor or Originator Signature
Project Manager NameSponsor or Originator Name
DateDate

Saturday, 1 February 2014

Project Risk Terms and Definitions

Project Risk Terms and Definitions


Terms and Definitions used regularly in construction projects and defined in PMI PMBOK


A project risk is a potential source of deviation from the project plan. Project risks can have a negative or positive impact on the project. Project risks that are negative are called threats. Project risks that are positive are called opportunities.Non-critical risks should be documented. They should be revisited and reviewed regularly.Risks are identified in all phases.Work-around refers to how to handle risks that have occurred but are not part of risk response plan. This happens in risk monitoring and control phase.




  • Amount at Stake: The extent of adverse consequences which could occur to the project. (Also referred to as risk impact).





  • Business Risk: The inherent chances for both profit and loss associated with a particular endeavor.





  • Contingency Planning: The development of a management plan that identifies alternative strategies to be used to ensure project success if specified risk events occur.





  • Contingency Reserve: A separately planned quantity used to allow for future situations which may be planned for only in part (“known unknowns”). Contingency reserves are intended to reduce the impact of missing cost or schedule objectives. Contingency reserves are normally included in the project’s cost and schedule baselines.





  • Deflection: The act of transferring all or part of a risk to another party, usually by some form of contract.





  • Expected Monetary Value: The product of an event’s probability of occurrence and the gain or loss that will result. For example, if there is a 50% probability it will rain, and rain will result in a $100 loss, the expected monetary value of the rain event is $50 (.5 * $100).





  • Impact Analysis: The mathematical examination of the nature of individual risks on the project, as well as potential arrangements of interdependent risks. It includes the quantification of their respective impact severity, probability, and sensitivity to changes in related project variables, including the project life cycle.





  • Insurable Risk: A particular type of risk which can be covered by an insurance policy. Also referred to as a pure risk.





  • Management Reserve: A separately planned quantity used to allow for future situations which are impossible to predict. (“unknown unknowns”) Management reserves are intended to reduce the risk of missing cost or schedule objectives. Use of management reserves requires a change to the project’s cost baseline.





  • Mitigation: Taking steps to lessen risk by lowering the probability of a risk event’s occurrence or reducing its effect should it occur.



  • Monte Carlo Analysis: A schedule risk assessment technique that performs a project simulation many times in order to calculate a distribution of likely results.





  • Opportunities: As related to risk, positive outcomes of risk.





  • Project Risk Management: Includes the processes concerned with identifying, analyzing, and responding to project risk.





  • Risk Event: A discrete occurrence that may affect the project for better or worse.





  • Risk Identification: Determining which risk events are likely to affect the project.





  • Risk Management Plan: A subsidiary element of the overall project plan which documents the procedures that will be used to manage risk throughout the project. Also covers who is responsible for managing various risk areas; how contingency plans will be implemented, and how reserves will be allocated.





  • Risk Quantification: Evaluating the probability of risk event occurrence and effect.





  • Risk Response Control: Responding to changes in risk over the course of the project.





  • Risk Response Development: Defining enhancement steps for opportunities and mitigation steps for threats.





  • Threats: As related to risk, negative outcomes of risk.





  • Total Certainty: All information is known.





  • Total Uncertainty: No information is available and nothing is known. By definition, total uncertainty cannot be envisaged.



  • Uncertainty: The possibility that events may occur which will impact the project either favorably or unfavorably. Uncertainty gives rise to both opportunity and risk.





  • Workaround: A response to a negative risk event. Distinguished from contingency plan in that a workaround is not planned in advance of the occurrence of the risk event.





  • Avoidance: Changing the project plan to eliminate the risk and protect the project objectives.





  • Transference: Shift the consequence of the risk and ownership to a third party. (E.g. insurance)





  • Mitigation: To reduce the probability/impact of a risk to an acceptable threshold. (E.g. prototype).





  • Exploit: This strategy may be selected for risks with positive impacts where the organization wishes to ensure that the opportunity is realized. This strategy seeks to eliminate the uncertainty associated with a particular upside risk by making the opportunity definitely happen. Directly exploiting responses include assigning more talented resources to the project to reduce the time to completion





  • Share: Sharing a positive risk involves allocating ownership to a third party who is best able to capture the opportunity for the benefit of the project. Examples of sharing actions include forming risk-sharing partnerships, teams, special-purpose companies, or joint ventures.





  • Enhance: This strategy modifies the .size. of an opportunity by increasing probability and/or positive impacts, and by identifying and maximizing key drivers of these positive-impact risks



Project Risk Terms and Definitions

Planning EngineerPlanning Engineer

مهندس تخطيطمهندس تخطيط

Planification IngénieurPlanification Ingénieur