Saturday 22 February 2014

Handle Scope Change Requests with Appropriate Discipline

Handle Scope Change Requests with Appropriate Discipline


 


When a project begins, you must gain agreement with your sponsor on project scope. The scope is defined at a high-level in the Project Charter or Project Scope Statement. At a low-level, the scope is detailed through the approval of the business requirements. Once these two documents are approved, you have enough information to understand scope through the remainder of the project.



However, like death and taxes, change is inevitable. There are two reasons. First, it is almost impossible to define ahead of time exactly what the final solution should look like, and so the requirements may change as the solution starts to evolve. Second, overall business conditions change over time. Some of this business change will force changes to the project scope in ways that are not known ahead of time.


 


Therefore, what do you say when the inevitable changes start to come in? If you say yes without taking into consideration the consequences to the project objectives, you may increase your chance of failure. If you say no, you may introduce conflict with the client and run the risk of delivering a solution that does not meet the client’s needs or satisfaction.


 


The right approach to scope change management is to not say “yes” or “no”. The better response is to follow a scope changing management process. This process should include:


scope change


 


-          Evaluate and understanding the business value of making the change


 


-          Estimating the impact on the project objectives like cost, time, and scope….etc.


 


-          Taking the final information to the project sponsor (or their designate) for an approval decision.


 


Scope change management is really the process of letting the sponsor make the decisions – once they understand all the facts and implications.


 


You should establish scope change procedures based on the size of the project. For small projects (maybe less than 250 effort hours or 25 calendar days), you do not need to worry about scope change as much. The project will likely start and end before the business can change much and most of the requirements are probably fairly well known. The project manager can quickly evaluate a small change request and work with the sponsor to determine if it should be accommodated.


 


For larger projects, scope change is a big deal, and must be managed probably. All stakeholders, including the sponsor, must be sensitized or informed to understand when a scope change request made. The scope change request process may have a number of steps and require a template or two. If the sponsor approves the change, the budget and timeline are changed accordingly. If the change is not approved, it is noted as such and the project continues on its way. You might be surprised how often the sponsor does not approve the scope change, once they understand the impact to the project.


 


Summary


 


Many project managers do a poor job of managing scope because they do not want to offend the client. However, that should not be a part of the scenario at all. Instead,  the project manager’s job is to make sure the scope change management process runs effectively,  and that the project sponsor has the information they need to make the best decision possible on  whether the scope change should be accepted ,you as a project manager must believe this rule “at begins of any project you and project sponsor have a progress elaborated project scope ,so it can changed at any time


By Ahmed Ibrahim ,PMP®,PMI-RMP®


For more information and projects management templates or forms, please you can visit


www.planningengineer.net


Article recourses


PMBOK 5th edition


http://www.mpmm.com/


www.projectmanager.com


 



Handle Scope Change Requests with Appropriate Discipline

No comments:

Post a Comment

Planning EngineerPlanning Engineer

مهندس تخطيطمهندس تخطيط

Planification IngénieurPlanification Ingénieur