Wednesday 27 November 2013

Understand how scheduling tools works-Draw network diagram yourself

All Planning Engineers, and most of project managers can create a Gantt Chart (Bar Chart) using different scheduling tools such as Primavera and Microsoft Project. However, only few of them really know how the scheduling software is calculating the network diagram in order to estimate the project duration, project floats, and critical path.




In this topic we will discuss how any software is calculating the network diagram in order to estimate project duration, float, and the critical path. Using the following figure of network diagram we will see how is the calculation works.

network diagram




Each circle represent a task, each line between tasks represent the relationship. For example Task S  need to be finished before task A can start, and Tasks B and C should be finished before task F can start and so on.

First of all, you need to draw a rectangular for each task as per the following figure.


Task ES = Early start


EF= Early finish


ID = task ID


Slack= Total Float


E= Task duration


LS= Late start


LF= Late finish




 

If we assumed the duration (E) for each activity as per the following:


























In order to calculate the values is each rectangular (task), you should first fill the duration (E), calculate Early Start (ES) and Early Finish (EF). This process is called Forward Calculation EF = (ES + D) – 1

After you Finish all the tasks, from the last one you need to go back and calculate the Late Finish (LF), Late Start (LS), and the Total Float (Slack). This process is called Backward Calculation LS = (LF – D) + 1


You should have a shape something like the following figure


network diagram


The Green color represent the Forward Calculation EF = (ES + D) – 1, and the yellow color represent the Backward Calculation LS = (LF – D) + 1




Try to solve this network diagram by yourself, this will help you to develop a common sense when you are dealing with scheduling software such as Primavera or Microsoft Project. when you finish you will be able to find the project total duration, which will be founded on task J Early Finish or Late Finish, and you will be able to define the critical Path.

Assuming that the project duration is 30, and the critical path is ACGHI, use both of them as a password 30ACGHI to open the following link and add your name to honor board icon smile


Add your name to the honor board from the following link: http://www.planningengineer.net/network-diagram-honor-board/



Honor Board



Understand how scheduling tools works-Draw network diagram yourself
TaskTask Duration E
A7
B11
C12
D9
E2
F10
G3
H2
I6
J8

No comments:

Post a Comment